Project: Dolphin House, Moreton Business Park, Hereford.
Client: Building Design Practice.
Contract Management: Supercraft Structures Ltd.
Supercraft Structures had a tight 12 week turnaround on this project to completely strip back to the structural steel skeleton and refurbish with new roof, steel cladding, aluminium windows, curtain walling and doors.
We were nominated as the glazing contractor and working in close co-operation with Supercraft and other sub contractors, were able to complete our aspect of the contract within the programme, ensuring that the building was handed over on time.
Smart Architectural Aluminium System used throughout incorporating approx 200 linear meters of ribbon windows, 20 square metres of curtain walling, main entrance doors and screening together with fire exit and personnel doors.